DLC staff are excited about scheduled plans to remodel the upstairs balcony in our open work environment. As you see in the 3D rendering above, the upstairs balcony will be removed and a set of two nearly floor to ceiling 8′ wide storefront style windows will be installed. The upper window portion will be able to open and close allowing us to maintain a degree of flexibility and open-ness between the upstairs and downstairs Design Space. The upstairs will be enclosed with additional floor to ceiling glass and a door located at the top of the internal staircase, just to the right of our red media booth.
Remodel Construction Schedule (as of Nov 17, 2015)
DLC staff are coordinating with Director of Facilities, Andrew Hernandez, and our contractor on a construction schedule that we hope will minimize disruption for our staff and for those who have plans to use the DLC in January.
- DLC balcony remodel work will begin Monday, December 14.
- Contractors will work over winter break to install new bank of floor to ceiling windows
- An on-schedule project is expected, though not guaranteed, to be completed by second week of January, 2016 – in time for Spring 2016 classes and community events
During construction, DLC staff will likely relocate to another location in the McGowan Building. Details about how staff can be reached will be updated once they are finalized.